Federal IT risk ratings: GAO finds gaps in oversight

GAO found more risk than CIO ratings indicated in 24 of 53 investments. Its October report calls for better rating quality and more timely updates.

Published Last updated

Federal IT risk ratings can lose their value when they stop reflecting the evidence behind a project. In an October 7 report, the Government Accountability Office found higher risk than the associated chief information officer ratings indicated for 24 of 53 selected investments. The finding raises a practical question for oversight teams: does the rating describe the investment now, or an earlier point in its history?

GAO-27-108416 examined 53 investments at 12 agencies, selected using fiscal year 2025 budget data and a threshold of at least $35 million in development activities. GAO’s assessments matched CIO ratings for 27 investments and indicated less risk for two. The sample should not be treated as a failure rate for all federal IT projects.

A rating needs an evidence date

GAO found that 21 of the selected CIO ratings had not been updated on time under agency processes. Two agencies also used rating processes that extended beyond quarterly intervals, contrary to Office of Management and Budget guidance. GAO issued 17 recommendations to nine agencies concerning rating quality and frequency.

For a program review, the rating date is therefore as important as the color or score. A current dashboard can still display an old assessment. Reviewers need to know when the underlying risks were evaluated, what changed after that evaluation and who is responsible for deciding whether a change warrants a revised rating.

Consider a modernization project whose last assessment preceded a delayed interface test. The project may still display a favorable rating even though the delayed test has changed the likelihood of meeting its schedule. The review question is whether the new evidence has been considered and documented. It is not enough to confirm that the dashboard itself loaded successfully or that a reporting field was populated.

Preserve the reasoning behind a disagreement

A difference between two assessments deserves explanation. Oversight staff should identify which risk evidence each assessment used, the period it covered and the criteria applied. That makes it possible to distinguish stale information from a substantive difference in judgment.

A useful record would connect the rating to the major risk, its potential effect on delivery and the action intended to reduce it. If the program believes a mitigation keeps the overall rating low, the record should explain the mitigation’s status and the evidence supporting that judgment. A planned action and a completed action provide different levels of assurance.

This is an operational recommendation drawn from the reporting problem, not a new scoring method imposed by GAO. Agencies still need to follow their applicable rating processes. The aim is to make those processes understandable enough that another reviewer can reconstruct the decision.

A new reporting system still needs reliable inputs

The report says OMB announced in April 2026 that it was taking steps to replace the IT Dashboard with a streamlined system, without providing a release timeframe. That announcement is not evidence that the replacement has launched or that existing oversight responsibilities have ended.

When a reporting platform changes, teams should preserve the relationship between investment identifiers, past ratings, evidence dates and open risks. Otherwise, a cleaner presentation can conceal a break in the history needed to judge whether a project is improving. A migration check should test that a reviewer can still follow a particular investment through time.

The same principle applies to automated reporting. An automated refresh can move data quickly while repeating an outdated judgment. Separating the time of data transfer from the time of risk assessment helps prevent that confusion. Reviewers can then ask for the missing assessment rather than mistakenly treating the latest upload as proof that the investment was reconsidered.

For the next portfolio review, the most useful preparation is a small set of traceable records: the current rating, its evidence date, material changes since that date and the decision on whether those changes alter the assessment. Those records make escalation possible before an inaccurate rating becomes an avoidable delivery problem.